  1. Summary of Total Bed/Service Requirements
  2. Summary of Reinvestments and Savings

1. Summary of Total Bed/Service Requirements

Frontenac, Lennox and Addington Counties Hospital Inpatient Bed Requirements 2003

Category of Beds
Sited in Kingston for 2003
Sited in Napanee for 2003
Total Required in Frontenac, Lennox and Addington 2003
Total in Operation in 1997-98

Acute Inpatient

398

40

438

415

Rehabilitation

45

-

45

46

Complex Continuing. Care

72

20

92

149

Adult Acute Mental Health

34

-

34

47

Longer-term Mental Health(excludes forensic beds)

46

-

46

225

Child & Adolescent Mental Health

3

-

3*

n/a

Sub-acute

41

3

44

n/a

Forensics

74

-

74 **

30

Total

713

63

776

912

Operating Rooms

17

1

18

18

* sited in Ottawa
** includes 44 beds transferred from the Brockville Psychiatric Hospital

Distribution of Long-Term Care Services in Frontenac, Lennox and Addington

 
Current beds/ spaces 1995
Proposed beds/spaces to 2003
Change
#
%

Complex continuing care

225

90

(135)

60% decrease

Long-term care

1,165

1,226

61

5.2% increase

Supportive housing/long-term home care

898

1,467

569

63% increase

2. Summary of Reinvestments and Savings

Summary of Required Reinvestments

Home Care

$889,631

Long-Term Care

$1,135,515

Sub-Acute Care

$3,163,820

Mental Health

$13,631,220

Information Technology System

tba

Total

18,820,186

Summary of Capital Reinvestment for Kingston Hospitals

 
Kingston General
KPH for Non-Acute
KPH for Ambulatory Care
Total

New construction

$16,424,001

$13,905,760

$11,555,775

$41,885,536

Renovations

$6,558,750

$10,067,500

$11,837,800

$28,464,050

Ancillary costs

$5,331,998

$5,561,796

$5,427,309

$16,321,103

Site development

$1,000,000

$1,000,000

$1,000.000

$3,000,000

Furnishings & equipment

$2,000,000

$500,000

$2,000,000

$4,500,000

Total capital estimates

$31,314,749

$31,035,056

$31,820,884

$94,170,689

Summary of Total Expenses and Savings

1995/96 Net Expenses *

$226,887,909

 

Clinical efficiencies

$9,533,161

 

Program transfers

$3,336,845

 

Support services efficiencies

$2,703,953

 

Administrative efficiencies

$13,889,866

 

Site closure

$3,159,954

 

Change in selected expenses1

$416,105

 

Rehabilitation

$1,608,246

 

Complex continuing care savings

$9,869,416

 

Mental Health

$13,631,220

 

TOTAL SAVINGS

$58,148,766

 

REVISED EXPENSES

$168,739,143

25.6%

* Net Expenses from Ontario Cost and Distribution Methodology
1 Selected expenses are overhead expenses not transferred to the receiving institutions during program transfers.

Back to the top


Back to the English News Releases Menu
Back to the English Main Menu
Go to the French Main Menu